Barnstaple Service Station

Earthworks carried out for the new EG Service Station in Barnstaple
default
default

Barnstaple Service Station

We worked alongside AKN Build to carry out the earthworks for the new EG Services

During the Summer of 2024, we carried out our 1st job working with AKN Build on their largest site to date.

About the Project

Gartell and Son carried out the work including a vegetation clearance before the topsoil strip, cut and fill of circa 10,000m³, ground stabilization, and removal of excess soil from the site. The cut and fill included the shaping of 2 new ponds and a swale. We worked around the existing services and through some really challenging west weather conditions.